Audit report, part 2: thousands of social homes built but not handed over, and water projects years late

Part 2 of 4 of our reading of the Director of Audit's 2024-25 report: what the auditor found in social housing, water pipes and dams, a sports complex and police equipment.

A building under construction in Pamplemousses

Photo: Benoît Prieur, CC0

In short

Part 2 of 4: Part 1 (3 November) covered the deficit, the debt and the interest bill.(1) This part covers what the auditor found in the projects people use: homes, water, sport and the police. Parts 3 and 4 follow on 6 and 7 November.

Social housing: by August 2025 the state agency NSLD had finished 3,086 homes, but only 41 had been handed to families.(1) For 1,822 of them, roads, drains and sewage works were not ready; the rest were still being allocated.(1)

Water: about 1,500 km of the 5,500 km of pipes are 50 to 80 years old.(1) The Rivière des Anguilles dam was on hold for 15 years and its cost rose from Rs 2.6 billion to Rs 7.9 billion.(1)

Smaller cases: a sports complex at Triolet took 11 years and cost Rs 71 million more than planned, and police equipment paid Rs 21.6 million in 2019 was only installed in 2024, when it was already out of date.(1)

Your wallet: each social home costs the state about Rs 2.72 million, while the family pays Rs 975,000.(1) For the 1,822 finished homes waiting for roads and drains, the state's planned share is about Rs 5 billion (our calculation).

This is part 2 of 4

Every year the Director of Audit, the official who checks how the government spent public money, publishes a report. The one on the 2024-25 accounts runs to 986 pages.(1) Part 1, published on 3 November, covered the public finances: a deficit of Rs 66.8 billion instead of Rs 26.8 billion, debt at 86.5% of GDP and interest taking 11.9% of regular revenue.(1)

Part 2 follows that money into projects you can see: social homes, water pipes and dams, a sports complex and police equipment. The pattern is much the same in each. The money is spent, and the result arrives late, or has not arrived yet. Part 3 (6 November) covers health, social aid and schools, and part 4 (7 November) covers food, waste, drains, the police and the courts.

Social homes built but empty

Start with housing. The state helps families in need to own a home through two state-owned companies: the National Housing Development Company (NHDC) and its subsidiary, the New Social Living Development Ltd (NSLD).(1) The NSLD builds the homes and the NHDC sells them to families.(1) To qualify, a couple or a single applicant must not already own a house or land, and since the 2025-26 Budget must have a basic income of up to Rs 48,000 a month, instead of Rs 40,000.(1)

What does a home cost? The NSLD was asked to build 12,000 homes, and by 30 June 2025 the state had transferred Rs 18.9 billion to it to pay for the construction of 8,000 of them.(1) Each home is estimated to cost Rs 3.69 million in all, including roads, drains and land. The family pays Rs 975,000 and the state pays the other Rs 2.72 million, or 73%, although the report notes that the 2025-26 Budget revised the state's subsidy to 67%.(1)

So how many families have a home? Very few so far. The report says no NSLD home was finished from 2021-22 to 2023-24.(1) By 7 August 2025, 3,086 were finished on 15 sites, but only 41 had been handed over to families, at Olivia.(1)

Why so few? A home cannot be lived in without the work around it, which the report calls offsite works: access roads, drains and a pumping station to carry sewage away. On 7 of the sites, 1,822 finished homes were still waiting for that work, with completion dates between August 2025 and March 2026.(1) On the 8 other sites, 1,264 homes had been passed to the NHDC to allocate to families. By August 2025, 797 cases had been approved and 394 letters of offer issued, but keys had been handed over for only 41 homes.(1) By 12 November 2025 the NHDC said it had approved 1,104 applications and issued 1,053 letters of offer.(1)

Empty homes also run down their guarantee. A builder must fix defects during a set period after completion, called the defects liability period. For 368 homes on 3 sites that nobody lived in yet, it ran out in October 2025.(1) The report does not say what defects, if any, were found.

Other sites are further behind. Contractors can receive an advance, a share of the price paid before the work starts. At Riambel, no work had started on 70 homes in September 2025, yet the contractor had already been paid 25% of the contract, Rs 56.2 million.(1) At Balisson and Tyack, 600 homes were between 9% and 24% built.(1) The ministry replied that 5,258 homes were finished by 8 January 2026, but the works around them were complete on only 3 sites, for 360 homes, and that it expects 3,698 homes, with the works around them, to be complete by June 2026.(1) It also says the contract for 870 homes at Balisson, Tyack, Souillac and Riambel was ended on 31 December 2025, so work there is on hold.(1)

Meanwhile the queue grew. The NHDC keeps a list of people who have applied for a social home. It rose from 40,937 applicants in July 2024 to 51,875 in June 2025, up 27%.(1) The ministry says the list includes people who no longer qualify or are no longer interested, and that it is being updated.(1)

The auditor also points to missing plans. There is still no National Housing Strategy, a long-term plan for what to build, where and for whom.(1) The auditor had also asked the ministry to check whether two companies were needed for the same job. The ministry says the NHDC's shareholders decided on 11 December 2025 to merge the NSLD into the NHDC.(1)

Old pipes and late dams

Water raises the same question: does the money produce results? The Central Water Authority (CWA) is the state body that supplies drinking water. It runs about 5,500 km of pipes, and about 1,500 km of them are 50 to 80 years old.(1) The report says these old pipes burst often and lose a lot of water.(1)

The report measures the loss as non-revenue water: water the CWA treats but loses through leaks or never bills, for example because of faulty meters or theft. As part 1 showed, that was 65.4% of the water produced in 2024.(1)

The CWA picked 500 km of pipes as the most urgent to replace in 2023 and 2024.(1) Rs 700 million of public money went to the CWA's own teams for part of the work. Two years later the CWA had still not given the ministry a final account of the kilometres laid or the cost, and the auditor saw pipes laid above ground in several places, not in trenches as agreed.(1) The plan was to cut water losses by 11% by June 2025, which would have brought the CWA about Rs 120 million of extra revenue. By October 2025 nobody had measured whether it did.(1)

A second programme used small contractors. Its ceiling was about Rs 1.2 billion, but the CWA signed contracts worth Rs 1.6 billion, about Rs 400 million more, without prior clearance from the Ministry of Finance.(1) The ministry could not say how many kilometres of pipe had been replaced, and the report notes that some roads where pipes were laid were left in a very bad state, which caused inconvenience to the public.(1)

Pipes carry water. Dams and reservoirs store it, so that rain from wet months can be supplied in dry ones. Here the problem is bigger. A master plan is a long-term roadmap, and the 2012 one for water, paid for with Rs 45 million of World Bank money, listed the dams Mauritius needed, most of them by 2025.(1)

It planned the Rivière des Anguilles dam for 2016. Instead the project was on hold from 2009 to 2024, its cost rose from Rs 2.6 billion to Rs 7.9 billion (2025-26 estimate), and it should now be finished at the end of 2029.(1) The ministry blames procurement, land, Covid-19 and funding.(1) The enlargement of La Ferme dam, planned for 2015, is now expected in 2028. The report says the main obstacle was people living inside the reservoir's boundaries, most of whom were relocated in 2024.(1)

Storage still depends on the rain. L'Express reported on 3 November that the reservoirs were only 51.4% full.(2)

A sports complex and police equipment

The same pattern shows up outside housing and water. The Ministry of Youth and Sports first planned a multi-sports complex at Triolet in November 2013, and it was finished in June 2025, more than 11 years later.(1) Part of the delay came from the first contract. The ministry cancelled it in May 2015, because the 2015-16 budget had no money for the project and a losing bidder had gone to court to stop it. The builder went to court and won, and in April 2025 the state paid Rs 19.3 million in damages, the compensation a court orders for breaking a contract.(1)

That is part of the extra cost. The new contract, signed in 2022 with the same builder, cost Rs 48.9 million more than the first one. With the consultant's fees, the extra cost is Rs 71 million in all.(1)

The new build was late too. It finished 835 days after the original date, 264 days after the extensions the ministry had agreed.(1) A contract can include liquidated damages, a penalty set in advance that the builder pays for each day of delay. Here it was Rs 200,000 a day, up to Rs 20.6 million. Yet the ministry had not deducted it, and only Rs 12.1 million was left to pay the contractor, not enough to recover it all.(1) The ministry says the extensions were granted for bad weather beyond its control, and that penalties apply to unjustified delays.(1)

Police equipment shows another version of the delay. In July 2018 the Commission of Inquiry on Drug Trafficking, the commission that investigated the drug trade in Mauritius, said the police urgently needed better technological tools.(1) In 2019 the police paid Rs 21.6 million, 90% of the price, for two pieces of specialised equipment designed to intercept calls.(1) One arrived in August 2019 and the other was not shipped. Both were only installed, remotely, in August 2024, five years later.(1)

By then the technology had moved on. The system could intercept calls on 4G but could not detect 5G phones, and the supplier advised buying a new one.(1) In December 2024 the supplier blocked its use until the last 10% was paid, and in September 2025 it was still unusable.(1) The auditor's root cause was that the police had no valid contract with penalty clauses for late delivery.(1)

What it means for you

So how do these findings reach a family? Take them one at a time, and keep to what the report says.

Housing. Picture a couple with a basic income of Rs 35,000 a month who own no house or land. They are under the Rs 48,000 ceiling and can apply.(1) An NSLD home costs them Rs 975,000. Spread over 25 years, that is Rs 3,250 a month before any interest (Rs 975,000 / 300 months, our calculation). The state pays the other Rs 2.72 million.(1) The report notes that the 2025-26 Budget revised the state's subsidy to 67% of the cost of a social home, so this 73% split may not apply to new sales; it does not give a new price.(1) But if their home is one of the 1,822 finished homes waiting for roads and drains, they cannot move in yet. For those homes alone, the state's planned share is about Rs 5 billion (1,822 x Rs 2.72 million, our calculation). If you have applied, check that your file with the NHDC is up to date, because it says it is clearing its list of people who no longer qualify or are no longer interested.(1)

Water. Think of the tap at home. When a pipe leaks, the water is lost before it reaches you, and the CWA also loses the money it would have billed. The report does not say your own supply was cut because of these findings. It says old pipes lose water, the dams meant to store more of it are years late, and L'Express reported on 3 November that the reservoirs were 51.4% full.(2) Until new dams are built, storage depends on the rain. Store some drinking water at home and report leaks to the CWA.

Taxes and borrowing. Part 1 showed that the state already spends Rs 21.9 billion a year on interest.(1) It borrowed Rs 76.3 billion in 2024-25, so some of the money behind these projects is borrowed and will be repaid, with interest, from taxes.(1) A sports complex that cost Rs 71 million more and police equipment that cannot be used are paid for the same way. These are not the biggest sums in the report, but they show money paid early, works finished late and too little checking of the results.

Want to check for yourself? The full report is public on the National Audit Office website, and part 1 of this series explains the debt behind these projects.

What parts 1 and 2 cover, and what is left

Together, the two parts so far cover the public finances (deficit, debt, interest, tax arrears, pension overpayments, income support) and four projects: social housing, water pipes and dams, the Triolet complex and the police equipment.(1)

They do not cover everything. Part 3 (6 November) covers health, social aid and schools. Part 4 (7 November) covers food, waste, drains, the police and the courts, including pesticides on farm produce and the compensation the state paid after court cases.

The full brief on MoBriefs has the charts, what it means for you, and every source.

Open in MoBriefs Get the free app

Sources

  1. National Audit Office: Certificate of Audit and Report of the Director of Audit on the accounts of the Government, financial year 2024-25 (February 2026)
  2. L'Express: Réservoirs, le taux de remplissage chute à 51,4 % (3 Nov 2026)

Related briefs

What climate change will cost Mauritius, and who pays17 November 2026 · The World Bank says Mauritius needs about US$5.6 billion of extra investment by 2050 to cope with a warmer, drier island with a rising sea, and that…Three US flood experts are here. The plan was never the problem: the drains are9 November 2026 · Three American water experts are in Mauritius until 23 November to help revise the Land Drainage Master Plan. The country already has the map of…Audit report, part 4: unapproved pesticides on farm produce, late drains and waste piling up7 November 2026 · Part 4 of 4 of our reading of the Director of Audit's 2024-25 report: food, waste, drains, the police, the courts and what the state paid after court…

Topics

Public finances and debt in MauritiusClimate, water and the environment in MauritiusAll briefs

Lire en français